A.0.80
B.0.16
C.1.60
D.0.10
您可能感興趣的試卷
你可能感興趣的試題
A.Parallel and Serial
B.Serial and Asynchronous
C.Parallel and Synchronous
D.Synchronous and Asynchronous
A customer has several single partition POWER5 and POWER6 processor-based systems housed in regional data centers and wants to consolidate into a single Power 770. They must minimize overall cost and the number of adapters, while ensuring a reliable infrastructure.
Which solution addresses the customer requirements?()
A.Move the storage into a common SAN and virtualize the I/O using a single VIO Server with dual NIC connectors and dual HBAs
B.Move the existing physical network and storage adapters to the new system and virtualize the I/O using a single VIO Server.
C.Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, each with dual NIC connectors and dual HBAs.
D.Move the storage into a common SAN and virtualize the I/O using dual VIO Servers, one with dual NIC connectors and the other with dual HBAs.
A customer would like to have the ability to permanently activate processor and memory resources as their workload increases.
Which of the following supports the customer requirement?()
A.Reserve Capacity on Demand
B.Utility Capacity on Demand
C.Capacity Upgrade on Demand
D.Uncapped Capacity on Demand
When a customer attempts to manage virtual machines, virtual images and system pools with the VMControl Express Edition, all operations fail except for managing virtual machines.
What is recommended to resolve this situation?()
A.Upgrade to VMControl Standard Edition
B.Upgrade to VMControl Enterprise Edition
C.Upgrade to latest version of VMControl Express Edition
D.Download the latest fixes for VMControl Express Edition
A.Manage multiple operating systems on a server
B.Manage energy consumption and network traffic to increase efficiency
C.Manage LPARs, operating systems and servers to reduce administration
D.Manage workloads across multiple servers to optimize resource utilization
最新試題
A customer is evaluating PowerVM and VMware to run a data warehouse application. Which feature of PowerVM should be highlighted as a differentiator?()
Which of the following items in a single enclosure Power 770 improves Reliability, Availability, and Serviceability?()
A customer wants to migrate their existing compute-intensive POWER6 570 to a Power 770. Which of their existing I/O adapters can be migrated to Power 770 enclosures?()
A customer is implementing a POWER Blade solution which requires the VIO Server to be mirrored on internal disk drives. Which Blade supports the requirement?()
A POWER7 processor has L1, L2 and L3 caches. Which of the three caches uses embedded DRAM (eDRAM) technology?()
A customer has an HMC-managed Power Systems server with 6 partitions. Four production partitions are subject to varying workloads throughout the day, and two are used for development and testing. The production applications have different licensing limitations on the number of physical cores that may be used. The development partitions can use no more than 1 core. The customer would like to dynamically optimize processor utilization within the licensing limits, with minimal operator intervention.Which of the following meets the customer requirement?()
Which of the following is a compelling reason to deploy IBM Systems Director Active Energy Manager (AEM) in a data center with high energy utilization?()
Using the following information: Performance data from an existing system that a new system will replace; Performance estimates that anticipate future workloads; Micro-partitioning and logical partitioning implementations.Which of the following allows a technical sales representative to create a system design which can be imported into an HMC?()
A data center includes a Power 750 server running AIX and Linux, and PS700 Blades running AIX. What can the customer use to update AIX and Linux, create and deploy LPARs, and set energy caps for both servers from a single console?()
A customer would like to configure an uncapped LPAR so that it can use 2 to 8 cores depending on the workload characteristics. With SMT4 enabled, what is the least amount of processing resources which can be configured for the LPAR?()