()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
A.Planned value
B.Earned value
C.Actual cost
D.Cost variance
您可能感興趣的試卷
你可能感興趣的試題
PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start
B.Finish-to-Finish
C.Start-to-Start
D.Start-to-Finish
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
A.estimating
B.defining
C.planning
D.sequencing
The () describes, in detail, the project's deliverables and the work required to create those deliverables.
A.project scope statement
B.project requirement
C.project charter
D.product specification
A.project management plan
B.contract
C.project human resource plan
D.project charter
The ()Process Group consists of the processes used to complete the work defined in the project management plan to accomplish the project's requirements.
A.Planning
B.Executing
C.Monitoring and Controlling
D.Closing
最新試題
Which of the following statement related to PMO is not correct?()
The process of()schedule activity durations uses information on schedule activity scope of work, required resource types, estimated resource quantities, and resource calendars with resource availabilities.
()from one phase are usually reviewed for completeness and accuracy and approved before work starts on the next phase.
In approximating costs, the estimator considers the possible causes of variation of the cost estimates, including() .
The()provides the project manager with the authority to apply organizational resources to project activities.
The() defines the phases that connect the beginning of a project to its end.
空白(2)處應選擇()
Project() Management is the Knowledge Area that employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.
The()process analyzes the effect of risk events and assigns a numerical rating to those risks.
PDM includes four types of dependencies or precedence relationships: (). The completion of the successor activity depends upon the initiation of the predecessor activity.